Habitat for Humanity, Millstone Basin Area

Monday, July 09, 2007

Building Update - July 7, 2007

Moss House
- All Bedrooms are painted
- Closet shelves started in one bedroom
- Kitchen cabinets in place
- All the molding is painted
- Front shutters are hung
- HVAC installed
- Electric meter in place

Next week:
- Finish final coat on hallway
- Closet shelving
- Bathroom closet door installed
- Check molding for touch ups
- Paint laundry room closet and touch up cieling
- Order carpet & flooring
- Hang & paint closet doors

D'Alessio House
- Sheetrocking and Spackling conitued

Next Week:
- More Spackling (fun)

posted by Mike Strada