Moss house
- Completed the last piece of siding
- Trimmed and installed attic access
- Puttied all nail holes in outside door frames
- Puttied all nail holes in window sills
- Completed all sanding (we are ready to paint)
This coming Saturday we will be apply the paint primer to all the interior walls.

D'Alessio House
- Siding started
- Window installation started
- Siding trim started
- Phone/TV wired

This coming Saturday more siding, windows, trim