Tuesday, June 26, 2007

Another Very Productive Week at Both Houses

Moss House
Completed this week

  • Interior doors installed
  • Base molding, hall char rail, and Kitchen/Living room Crown molding installed
  • All rooms received at least on coat on final paint, Ceilings and walls
  • The interior doors got a first coat of paint

Next week

  • We will need to put a second coat on all the walls and please check the ceilings
    Start paint the base molding
  • Second coat on doors
  • Bathroom Ceiling needs a coat of the Satin Finish paint

D'Alessio House

From the architect's (Bill Gittings) report

Today we finished the insulation and misc. framing. I will call in for inspections for Tuesday so that we can start drywall. We are on for the revised schedule to finish at the end of August for the homeowner's kids to start school in September. Tom and Tim led volunteers to finish a few eaves, the side wall siding, and siding up to the front porch roof. We need to come up with a way to finish above the porch roof.

Ed and I will call in the drywall order and order cabinets.

filed by Mike Strada