Building Update - April 22, 2007

Moss House
We continued to sheetrock. Status as of today.
Both back bedrooms are completely rocked, closets and all.
Hallway is completely rocked from bathroom to Kitchen.
Master bedroom is 75% rocked
Laundry room just needs rock on front of furnace room.
Some taping complete in back bedrooms
Kitchen and front vestibule not touched
Next Saturday we will continue to rock. Eric I will need you there to supervise.

D'Alessio House
Ground Breaking Ceremony was held Sunday
Plumbers put in rough plumbing
Bill is calling for inspection on Monday for Tuesday inspection
Backfill plumbing trenches and pour slab on Wednesday
Friday layout house on slab
Saturday start Framing

filed by Mike Strada