Building Update - June 18, 2007

Moss House
- The entire interior has been primed
- All window sills have been caulked
- Ready for final coat

This weeks events
- Monday night Tara, Kathy, and Linda are meeting to pick out paint and carpet/vinyl colors
- Tom will have all the paint there by Friday
- Eric is having the doors and trim delivered and installed by Friday
- Friday night about 5:00 pm I am going to over and start cutting out the ceilings so Saturday goes faster - If anyone wants to come call my cell BEFORE you come 609-903-0287
- Saturday we will be applying the final coat of paint on all the rooms
- Eric is also working on getting the gutter guy over
- HVAC/Electric will be completed next week
- We are going to try to get everything completed, then do the flooring

D'Alessio House
- Siding was almost complete Saturday when I left, some minor spots to complete
filed by Mike Strada