Moss House
- Exterior doors painting completed
- Kitchen cabinets secured in place
Next Week
- Install kitchen counter top
- Closet doors
- Bathroom work

D'Alessio House
- Interior painting completed

Misc
- Both the trailers are empty and can be removed.