Construction Update - Feb 25
We made more progress this weekend on the Siding. The back wall is 3/4 complete. We have several sides started. The mud was more of a hindrance that the cold.
The electrician was there this week and the electricity is now roughed out.
We moved everything out of the Brown office trailer to the new trailer. The brown office will be removed the week or next. Bill and the QOM team will make sure we are not without electricity, but it looks like we might have to use a portable heater for heat in the office.
Next weekend activities:
- Put shingles on the roof ridge
- Install kitchen window and front door
- Continue siding
- Wednesday night the QOM Build team meets
We need volunteers for next Saturday. Send an email to: info@habitatmba.org if you're interested.
-- posted by Michael Strada
The electrician was there this week and the electricity is now roughed out.
We moved everything out of the Brown office trailer to the new trailer. The brown office will be removed the week or next. Bill and the QOM team will make sure we are not without electricity, but it looks like we might have to use a portable heater for heat in the office.
Next weekend activities:
- Put shingles on the roof ridge
- Install kitchen window and front door
- Continue siding
- Wednesday night the QOM Build team meets
We need volunteers for next Saturday. Send an email to: info@habitatmba.org if you're interested.
-- posted by Michael Strada