Construction Update - Jan 7

Last weekend, we continued framing inside the house. The kitchen, living room and master bedroom are ready for Sheetrock and we got some nailers up in the other rooms.

Thanks to Torry, Emil, and Tom for this weekend. You all are missing the fun of working in T-Shirts in January.

The plan for next weekend is roofing. Eric will have the roofing supplies there by Saturday, so we will be working both Saturday and Sunday.

Other activities:

  • Mike and Tom are working on getting the appliances
  • Emil has the Queenship of Mary house plans loaded into CAD and provided feedback to Bill G.
  • Mike has contacted a company that deals with trailers. Found them thru HFHI

- filed by Mike Strada