Saturday, January 13, 2007

January 13

Folks,
We got rained out today for the most part but we did get some stuff done. One side of the roof has its ice shield and drip edge installed, we installed nailers in the dormers for the step flashing, and we continued to work on the other rooms for sheetrock nailers.

We ended up working until 2:30. There was about 10 of us there. We cancelled Sunday due to the whether.

Next week we will be shingling the roof.

No pictures due to rain.

---- filed by Mike Strada