During the week we plan on the following:

  • Get the electrician and plumber on site for the roughing out
  • Arrange for sill trim for the siding
  • Arrange to have the kitchen window and front door onsite for Saturday

Saturday Feb 24 is a full work day stating at 9 am. We will continue on siding work and get the doors in place and kitchen window.

Sunday Feb 25 we will continue siding with the help of the youth group. This will only be a half day build starting at 12:30 after the Pancake Breakfast (pdf).