A lot of activity this weekend on the Moss house:

* Accomplishments
o All roofing debris cleaned up
o Octagon window installed
o Side entry door installed
o All starter strips for siding in place
o Most windows completed with J-Channels
o Most missing tar paper replaced
o More nailers completed inside the house
o Back wall sided up to top of windows
o South side wall siding started
o North side wall has first row of siding
o Landscaping plan started

Miscellaneous
- The Master Gardens were one the Groups this week. Tom M. met with Linda from MG and started the landscaping plan
- Tom M. is also going to follow up with H&H for appliances the week of the 18th
- Kathryn was at the site and was very pleased about the progress and the color of the house.
- QOM (Bill) submitted their plans to East Windsor on Monday
- QOM team needs to dig where the Office trailer is. Tom T. from their team has made progress in plans for getting it out. Trying to this done before the end of February, target by 2/18