Habitat for Humanity, Millstone Basin Area

Sunday, December 03, 2006

Building Report - Dec 2

This weekend we made more progress. We installed the windows in the bedrooms, and bathroom. Two thirds of the house is wrapped and ready for siding. The roof is still proving to be a challenge. Eric and Roberto had hard time getting the Trusses over the Kitchen and Family room. They we will have to come back during the week to complete this. More work was done on the roof over the Master bedroom, we are almost complete and ready for shingles.

Next weekend we will complete the sheathing on the roof and start putting the shingles on the roof. Eric will have some Toll pros get the trusses straightened out during the weekend and have a roofer come over to get the shingles started.

-- Filed by Mike Strada