Accomplishments
- All interior door knobs installed
- Exterior door locks installed
- Kitchen ceiling paint touched up and lights re-installed
- Door stoppers installed
- Kitchen cabinet knobs installed
- Kitchen ceiling fan installed
- Closet doors painted
- Breanna's closet doors installed, this
- Purchased tub surround and tub fixtures
- Purchased kitchen sink
This week coming
- Counter top to be delivered Wednesday
- Install counter top, sink, faucet
- Install tub surround and fixtures
- Install Master Bedroom closet doors
D'Alessio House
- Started "finishing work"
- Painting trim and wall touch up
This week coming
- Excavator coming for grading/driveways
- Cabinet installation
- More finishing work on Saturday
filed by Mike Strada
Accomplishments
- All interior door knobs installed
- Exterior door locks installed
- Kitchen ceiling paint touched up and lights re-installed
- Door stoppers installed
- Kitchen cabinet knobs installed
- Kitchen ceiling fan installed
- Closet doors painted
- Breanna's closet doors installed, this
- Purchased tub surround and tub fixtures
- Purchased kitchen sink
This week coming
- Counter top to be delivered Wednesday
- Install counter top, sink, faucet
- Install tub surround and fixtures
- Install Master Bedroom closet doors
D'Alessio House
- Started "finishing work"
- Painting trim and wall touch up
This week coming
- Excavator coming for grading/driveways
- Cabinet installation
- More finishing work on Saturday