Building Update - Aug 20, 2007

Moss House
Accomplished
- Kitchen cabinets and counter top installed
- Kitchen sink installed
- Tub surround installed
- Closet doors hung and guides installed
- Outside walkway installed
- Driveway dug
- Shed pad installed
- Most of yard seeded
This week
- Chalk tub surround
- Spackle tub corner
- Install bath vanity and sink
- Install propane tanks and connect to house
- Do touch ups in kitchen

D'Alessio House
Accomplished
- Flooring installed
- Cabinets installed
- Painting complete
- Driveway/walkway installed
- Shed pad installed
- Yard seeded
- Mailbox installed
- Appliances delivered
This week
- Counter top installed
- Rug installed
- Power and water to house
- Propane connected to house (THURSDAY)
- Inspections