Wednesday, April 25, 2007

Building Update - April 22, 2007

Moss House
We continued to sheetrock. Status as of today.
Both back bedrooms are completely rocked, closets and all.
Hallway is completely rocked from bathroom to Kitchen.
Master bedroom is 75% rocked
Laundry room just needs rock on front of furnace room.
Some taping complete in back bedrooms
Kitchen and front vestibule not touched
Next Saturday we will continue to rock. Eric I will need you there to supervise.

D'Alessio House
Ground Breaking Ceremony was held Sunday
Plumbers put in rough plumbing
Bill is calling for inspection on Monday for Tuesday inspection
Backfill plumbing trenches and pour slab on Wednesday
Friday layout house on slab
Saturday start Framing

filed by Mike Strada

Labels:

Tuesday, April 17, 2007

Building Update - April 15, 2007

Another big progress weekend. We had the Rutgers crew to help and some really good individuals which worked out well. Sister Mary from QOM was there all day working with us, she will be an asset going forward, she comes with some skills, mechanical and spiritual. Kathryn Moss and the kids were there helping and seeing the progress. Another highlight was Eric brought T-Shirts Toll had made for the project, everyone appreciated getting one of these. - Thank you Eric

Moss House
- Sound insulated the bathroom walls
- Sheetrocked the tub area and ceiling in the bathroom
- Sheetrocked the two back bedrooms (no closets)
- Started to tape one bedroom
- Sheetrocked the master bedroom ceiling and upper walls
- Tom M. took pictures, so when I get them I will post them

Next weekend
- We will continue sheetrocking
- Tom M. and I are meeting with H&H about appliances on Thursday.
- Eric will try to get some Toll folks to sheetrock the upper part of the Kitchen/Family room during the week, if not on Saturday

D'Alessio House
- The foundation walls are in
- The excavator(Greg) worked Saturday to repack the backfill in the foundation
- If weather permitting, inspection and foundation plumbing will be done this week
- Greg spread stone from the road up to the Moss house so we don't have to walk through mud to get there
- Unfortunately due to the weather the Ground Breaking had to be cancelled today. It will be rescheduled

filed by Mike Strada

Labels:

Sunday, April 15, 2007

Groundbreaking Ceremony Postponed

We have decided to postpone the groundbreaking ceremony for the D'Alessio house that was scheduled for today because of the weather.

We will post a new date shortly.