Building Update - Sept 9
Moss House
Accomplishments
- 90% of the plumbing was complete - Missing Dryer connection and Furnace connection and need to turn water on
- Mudroom closet doors are ready for final hanging and adjustments
- All bathroom fixtures except towel rack installed
- On Saturday walked thru outstanding items with Kevin from Toll at Moss house
This week
- Complete plumbing Monday/Tuesday
- Medicine cabinet installed Monday
- Dishwasher installed Monday
- Window fixed and screens installed Monday/Tuesday
- Washer/Dryer installed Wednesday
- Gas tanks installed Wednesday
- Final inspection Thursday - C of O by Friday
- Saturday - re-key locks for Kathryn
- Saturday morning I will need help moving the final supplies to the storage facility
D'Alessio House
- Sharon moved in on Saturday -- What else could be said -- CONGRATULATIONS QOM team on a great job
Accomplishments
- 90% of the plumbing was complete - Missing Dryer connection and Furnace connection and need to turn water on
- Mudroom closet doors are ready for final hanging and adjustments
- All bathroom fixtures except towel rack installed
- On Saturday walked thru outstanding items with Kevin from Toll at Moss house
This week
- Complete plumbing Monday/Tuesday
- Medicine cabinet installed Monday
- Dishwasher installed Monday
- Window fixed and screens installed Monday/Tuesday
- Washer/Dryer installed Wednesday
- Gas tanks installed Wednesday
- Final inspection Thursday - C of O by Friday
- Saturday - re-key locks for Kathryn
- Saturday morning I will need help moving the final supplies to the storage facility
D'Alessio House
- Sharon moved in on Saturday -- What else could be said -- CONGRATULATIONS QOM team on a great job
Labels: Building report
0 Comments:
Post a Comment
<< Home