Building Update - Sept 9

Moss House
Accomplishments
- 90% of the plumbing was complete - Missing Dryer connection and Furnace connection and need to turn water on
- Mudroom closet doors are ready for final hanging and adjustments
- All bathroom fixtures except towel rack installed
- On Saturday walked thru outstanding items with Kevin from Toll at Moss house
This week
- Complete plumbing Monday/Tuesday
- Medicine cabinet installed Monday
- Dishwasher installed Monday
- Window fixed and screens installed Monday/Tuesday
- Washer/Dryer installed Wednesday
- Gas tanks installed Wednesday
- Final inspection Thursday - C of O by Friday
- Saturday - re-key locks for Kathryn
- Saturday morning I will need help moving the final supplies to the storage facility

D'Alessio House
- Sharon moved in on Saturday -- What else could be said -- CONGRATULATIONS QOM team on a great job

Labels:

Mr. John - An unsung hero of our build site

Something perhaps we've taken for granted for too long is the donation of portable restroom services on our work sites.

Mr. John, of Keasbey, NJ, has been donating their services to us for years.

I found on their Web site that Habitat is one of the charities they support as a company. They donate their services not just to Millstone Basin, but to many affiliates in New Jersey. The also support other charitable endeavors.

Well done. Community support comes from so many places.

Labels: ,

Sunday, September 16, 2007

Building Update - Sept 15, 2007

Moss House
Accomplishments
- Installed towel rack in bathroom
- Installed Medicine cabinet
- Installed hardware on Mudroom closet doors
- Emptied remaining tools/debris
- Installed shelf in bathroom closet
- Vacuumed every room

This coming week
- Monday - H&H install gas tanks and test appliances
- Install screens
- Tuesday/Wednesday - Final inspections
- Remove bumps in linoleum

Don't forget next Saturday 9/22, 3:00 - 6:00, Volunteer Recognition at the East Windsor Elks. Guaranteed to be a good time and we won't even make you work.

filed by Mike Strada

Labels:

Saturday, September 15, 2007

Queenship of Mary's Picture Page

There are dozens of pictures of the D'Alessio house during its four-month construction period posted on the Queenship of Mary 25th Anniversary Web site.

Wednesday, September 12, 2007

Many Thanks to our Supporters on the D'Alessio House

We'd like to thank the following companies and people who donated services and materials to the completion of the D'Allesio, which we just completed.
  • AIMCO: paint.
  • Bill Gittings of Gittings & Associates: architecture services
  • Conley Electric: electrical installation labor.
  • Daniel Bakaj of D & J Home Remodeling: services to teach volunteers and oversee siding installation.
  • Henderson and Bodwell: Site Engineering
  • Jim Bryde of Bryde Construction: framing, trim, and overall help.
  • Johnson Farms: foundation plantings.
  • Linda Principe of Linda Principe Interiors: mini-blinds for main areas and design services.
  • Marty Flatley of Marty’s Roofing and Maintenance: services to teach volunteers and oversee roofing installation.
  • Master Gardener: landscaping design and leadership
  • Mrs. G’s and Whirlpool: appliances.
  • Sharbell Development: lumber for sheds, trailer, and excavating.
  • Tindall Ranson Plumbing and Heating: plumbing installation.
The following also helped us by discounting their products and services:
J W Poole Mechanical Contractors: heating system; Bradco: roofing and siding supplies.; Home Depot of East Windsor: lumber supplies; National Building Supplies: drywall supplies; General Floor Wholesale: carpet and flooring; Silverline: windows; SCI Custom Kitchens: cabinets, counter, and installation; and The Gutterman: installed gutters and leaders